South District WWTP Oxygen Production Upgrades

Bid Date: March 28, 2017

Bid Time: 2:00 p.m.

Location: Miami, FL

Architect/Engineer: TBD

Chief Estimator: Joe Daigneault, 802.651.1221, jdaigneault@pcconstruction.com

Project Details

The South District WWTP Oxygen Production Upgrades project includes a new electrical building, installation of an owner-furnished centrifugal compressor, and overhaul of the existing centrifugal compressor. General trades involved include, but are not limited to: sitework, demolition, structural concrete, masonry, miscellaneous metals, roofing, doors and windows, architectural finishes, painting, process mechanical piping and equipment, HVAC, plumbing, electrical and instrumentation.

Hyatt Place Hotel

Bid Date: March 30, 2017

Bid Time: 4:00 p.m.

Location: Poughkeepsie, NY

Architect/Engineer: Alestalo & Etzel Architects

Chief Estimator: Todd Riordan, 802.651.1239, triordan@pcconstruction.com

Project Details

The Hyatt Place Hotel project includes the construction of a new, four-story, 60,000-square-foot Hyatt Hotel along South Road (Route 9) in Poughkeepsie, New York. The Hotel will feature 93 individual guest rooms, a swimming pool and fitness center, a lounge, meeting spaces, and a kitchen.

West Point Arvin Annex Athletic Center Building 673 Renovation

Bid Date: March 31, 2017

Bid Time: 12:00 p.m.

Location: West Point, NY

Architect/Engineer: Steffian Bradley Architects

Chief Estimator: Jeff Picoraro, 802.651.1224, jeffpicoraro@pcconstruction.com

Project Details

The West Point Arvin Annex Athletic Center Building 673 Renovation includes the interior renovation and fit-out of the historic 20,000-square-foot Arvin Annex Building for use as a West Point Division 1 sports strength training and conditioning facility. This new facility will include locker rooms, team conference rooms for multiple sports programs, and new mechanical, plumbing and electrical systems. Phased demolition and temporary structural bracing will be required to expand the lower level.

Springtree WTP Gravity Belt Thickening Upgrades

Bid Date: April 5, 2017

Bid Time: 2:00 p.m.

Location: Sunrise, FL

Architect/Engineer: Hazen and Sawyer

Chief Estimator: Joe Daigneault, 802.651.1221, jdaigneault@pcconstruction.com

Project Details

The Springtree WTP Gravity Belt Thickening Upgrades project includes the demolition of the aerobic digester tank, aerobic digester blower building and aerobically digested sludge transfer pump station. Work also includes the removal and replacement of two polymer preparation systems in the existing gravity belt thickening building and three existing gravity belt thickener feed pumps, as well as miscellaneous civil, mechanical, structural, and electrical work.

Noman Cole Solid Processing Rehab Phase II

Bid Date: April 12, 2017

Bid Time: 2:00 p.m.

Location: Fairfax, VA

Architect/Engineer: Arcadis

Chief Estimator: Joe Daigneault, 802.651.1221, jdaigneault@pcconstruction.com

Project Details

The Noman Cole Solids Processing Rehab Phase II project includes the demolition and replacement of the scum troughs, pumps, baffles, and piping associated with the primary and secondary clarifiers. The existing dissolved air flotation thickener systems and thickened waste activated sludge pumps will be replaced in Buildings Q1 and Q2. General trades involved with this work include, but are not limited to: sitework, demolition, structural concrete, masonry, miscellaneous metals, roofing, painting and coatings, architectural finishes, process mechanical piping and equipment, hoisting equipment, HVAC, plumbing, electrical and instrumentation.

Sawgrass WTP Ion Exchange

Bid Date: April 19, 2017

Bid Time: 2:00 p.m.

Location: Sunrise, FL

Architect/Engineer: Carollo Engineers

Chief Estimator: Gerry Torres, 802.651.1381, gtorres@pcconstruction.com

Project Details

The Sawgrass WTP Ion Exchange project includes the construct a new oxidation, pre-filtration, and ion exchange treatment system as well as a cleaning system for the existing degasifiers. Work also includes related electrical, instrumentation, and controls components; a new ammonia analyzer; and coating two existing ground storage tanks.

Broward County Remote Storage and Pumping Station 1A1 and 1B1 Generator Replacement

Bid Date: April 21, 2017

Bid Time: 2:00 p.m.

Location: Fort Lauderdale, FL

Architect/Engineer: CDM Smith

Chief Estimator: Joe Daigneault, 802.651.1221, jdaigneault@pcconstruction.com

Project Details

The Broward County 1Aa and 1B1 Generator Replacement project includes the removal and replacement of an outdoor generator, booster pumps and other incidentals at two sites. The scope of work includes, but is not limited to: demolition, concrete, piping, electrical and instrumentation. General trades involved include: concrete cutting, concrete, paints and coatings, process mechanical piping and equipment, electrical and instrumentation.

New Lewiston Elementary School

Bid Date: May 3, 2017

Bid Time: 2:00 p.m.

Location: Lewiston, ME

Architect/Engineer: Harriman Associates

Chief Estimator: Kyle Nolin, 802.651.1303, gtorres@pcconstruction.com

Project Details

Project details are currently unavailable.